Keeping to schedule

Published: 19-Apr-2010

Manufacturing for multiple clients requires constant attention to planning and scheduling. Preactor’s dedicated software is keeping Lonza on track

Manufacturing for multiple clients requires constant attention to planning and scheduling. Preactor’s dedicated software is keeping Lonza on track



As a leading lifescience supplier, Lonza’s products and services range from cell line construction to final product manufacture. Its site span the world, with its facility in Slough in the UK being one of several that deal with the biopharmaceutical division of Lonza Custom Manufacturing. This division works with customers on any, or all, of the stages in the development of a biopharmaceutical product. This may be a product for which Lonza applies its platform processes or a product for which the customer transfers a series of set processes. In the most usual case, the customer may require Lonza to develop both the product and the set processes.

While recognising that customers can work with Lonza at any or all stages of a product’s development, the general process flow begins with the required cell line construction. There then follows an in-depth analysis of product quality before selecting a cell line to progress to purification, pilot and then finally the manufacturing stage.

Suzanne Kennedy-May is a group leader within the analytical development department at Lonza Biologics in the UK. ‘We are driven by the customer’s requirements and a project may take many months or even years. The company is also often working on multiple projects.’

Some projects are, however, driven by a specific and fixed timescale – for example the development of a product for clinical trials in order to obtain a biological licence. Each project takes place in the context of Good Manufacturing Practice (GMP) whereby every factor is predefined and must be rigidly adhered to. This extends to each step of the developmental and manufacturing process, the equipment used, its calibration regime, including verification checks, the skill level of the scientists involved and the validation of the assay.

A key component is, therefore, the accurate scheduling of the steps within each project to ensure deadlines are met. Kennedy-May outlines the scheduling challenges faced by her department: ‘We have a high volume of assay requests and it is vital we manage this so that we can accurately identify the level of work we can undertake. We also maintain a training matrix for our scientists to ensure that we know their capabilities and can schedule accordingly. Finally, we have to be able to react to any changes in the schedule that may affect deadlines. Failing to hit any deadline has an impact on the project and indeed the company.’

developing better processes

Prior to investing in Preactor planning and scheduling software, all analytical groups had relied on Excel spreadsheets to generate and manage their respective schedules with each group doing this in a different way. For Kennedy-May, this meant manually transcribing the details for each assay as generated by the company’s bespoke Assay Request System, which could take half a day to complete depending on volume of requests.

The schedule was generated once a week and as Kennedy-May notes, ‘would be accurate only if everyone involved had accurately updated their requests and availability beforehand, which wasn’t always the case. The reality is that people may forget to update when they were on a training course, on holiday and of course people get ill.’

All of this meant that the schedule would then have to be manually updated with the impact on every other project manually calculated and entered into the spreadsheet. When added to the potentiality of changes such as request cancellations, timeline changes and equipment failure, the schedule might have to be updated on a daily basis.

The situation had long been recognised as less than ideal and in 2008 a decision was made to look for a better alternative. After a thorough review of potential systems, Lonza chose Preactor’s Advanced Planning and Scheduling (APS) system based on the planning capabilities of the software, the wide experience Preactor had in the industry, and for the ability the company had, as the software author, to work with Lonza in developing and refining some of its processes.

‘We didn’t want a system that would just mimic our existing processes – we wanted a system that would enable us to develop better processes and to then allow us to work according to these,’ says Kennedy-May.

Following a provisional meeting between key personnel within Lonza and Marcus Block of Preactor, it was agreed to commence implementation in January 2009 using Block's skills on a consultancy basis. Each month, Block would liaise with Lonza and develop a further refined version of the Lonza planning process on Preactor, which Kennedy-May and her team could then test extensively over the following month. During this time, Block also liaised with the developers of Lonza’s bespoke Assay Request System. An automatic link was developed so that all relevant information could be directly imported to the Preactor system.

Kennedy-May is positive about the implementation process and the willingness of Block to fine tune Preactor. Lonza went live with with the system in June 2009 and for the first month, Kennedy-May also ran the spreadsheet in parallel: ‘The reality was that Preactor worked exactly as we planned it would work.’

One of the first differences was the automatic updating of information from the Assay Request System, which saved time each day in manually updating the spreadsheet. The team was trained from the outset to check the Preactor viewers for real-time project information.

Not only did this also encourage each team member to take more responsibility for keeping the system up to date with their own calendar activities, it also meant that Kennedy-May could simply send a general alert to everyone to consult the viewer if a significant change had happened. Because Preactor can update the entire schedule automatically, she no longer needed to communicate to each individual person concerned the impact on the schedule and how it might affect them individually.

This increase in visibility has also helped her team to become more aware of what work is coming down the pipeline and to prepare proactively. A good example of this would be the ability of individuals to check the schedule on a Friday to see what is required the following week and to book any equipment in good time. Moreover, if a last minute change had happened, it means that they can react in advance, whereas with the previous system the first anyone might know about a problem would be when something didn’t happen as scheduled.

This increase in visibility is also beneficial when dealing with customers requiring updates on a project; with Preactor it is possible to identify not just which process a project is at, but how far through the process the project is.

While adamant that Preactor has increased visibility and saved time for scheduling preparation tasks, Kennedy-May stresses that the real benefits of Preactor, thus far, have been those concerned with enabling her and her team to plan more effectively and efficiently – so much so that Lonza is actively considering extending its use of Preactor not just to the other teams in this department of the company but also to different business divisions.